by adminXXX | May 7, 2020 | News
Progress Update May 2020 Structure 1 – Deck upstands and backfilling Structure 5 – starting east and west abutment bases Structure 8 – Pour south abutment Structure 9 – Complete beam instalment and start wingwall construction and backfilling Structure 10 –...
by adminXXX | May 7, 2020 | News
Traffic Management Update May 2020 Teeavan Road will close at its junction with Magheramore Road, between Monday 18th May at 0700hrs to Friday 22nd May 2020 at 1900hrs. During the closure a signed diversion will be in place via Teeavan Road, Crebarkey Road and Chapel...
by adminXXX | Apr 18, 2020 | News
Progress Update April 2020 Structure 1: Pouring diaphragm and decks Structure 5: Completing temporary works for slope stability and to start abutments Structure 7: Piling of both abutments are complete, pouring bases and start abutments Structure 8: Commencing with...
by adminXXX | Mar 18, 2020 | News
Joint Project Team Statement from DFI, AECOM and SWS JV Given the current situation around Covid 19, we’d like to clarify that construction of the A6 Dungiven to Drumahoe Dualling project will continue. As the health & safety of personnel and the public is our...
by adminXXX | Mar 9, 2020 | News
Traffic Management Update March 2020 Tirbracken Road will close between the junction of Gortica and Lismacarol Road on Friday 13th March at 1900hrs to Monday 16th March 2020 at 0600hrs. During the closure a signed diversion will be in place via Tamnaherin Road and the...