Progress Update April 2022

Apr 14, 2022 | News

 

 

 

Earthworks cut and fill operations are substantially complete with excavation works ongoing at Dungiven (Zone F), Drumahoe and Tamnaherin (Zone A). Along with pond excavation works in the Feeny Road area (Zone E) and Dungiven (Zone F) area.

Mainline drainage works substantially complete with outfall works to ponds ongoing at Burntollet (Zone B) and Dungiven. Side road drainage is ongoing at Dungiven and Drumahoe and further works to access tracks are continuing at Munreery (Zone E). Along with side road works ongoing at Tamnaherin, Drumahoe (Zone A) and Dungiven (Zone F).

Accommodation works are ongoing at Tamnaherin (Zone A) and Baranailt Rd (Zone D). Pavements works progressing from Tamnaherin to Claudy, with Claudy to Dungiven substantially complete with fencing operations ongoing around Tamnaherin.

NIW diversions and new installations are underway at Tamnaherin (Zone A) and landscaping activities ongoing throughout site. Line marking substantially complete from Claudy to Dungiven with works ongoing between Tamnaherin to Claudy. Signage and ITS to follow.

Structure 01

Substantially complete and being used by traffic 

Structure 02

Substantially complete and being used by traffic 

Structure 03

Paving and verge concrete to eastern verge to be completed mid-April 2022, being used by A6 traffic, side road works continue. 

Structure 04

Substantially complete and being used by traffic

Structure 05A

Substantially complete and being used by traffic

Structure 05B

Verge infill, barrier installation and concrete to be completed mid-April 2022, surfacing ongoing.

Structure 07

Installation of kerbs, ducting and verge infill to be completed mid-April and ready for surfacing end-April 2022, side road works into June 2022.

Structure 08

Paving works ongoing planned to be available to traffic in June 2022.

Structure 09

Substantially complete being used by traffic

Structure 10

Kerbing, ducting and verge concrete to be completed early May 2022

Structure 11

Substantially complete, traffic flowing through side road

Structure 12

Substantially complete, traffic flowing through side road

Structure 13

Substantially complete, traffic flowing through access lane

Structure 14

Substantially Complete, traffic flowing through side road

Structure 15

Substantially complete traffic flowing through side road

Structure 16

Substantially Complete, traffic flowing through side road

Structure 17

Substantially complete

Structure 18

Substantially complete being used by traffic

Structure 19

Substantially complete being used by traffic

Structure 20

Substantially complete being used by traffic

Structure 21

Substantially complete being used by traffic

Structure 22

Substantially complete, traffic flowing through access lane