Progress Update April 2022

Earthworks cut and fill operations are substantially complete with excavation works ongoing at Dungiven (Zone F), Drumahoe and Tamnaherin (Zone A). Along with pond excavation works in the Feeny Road area (Zone E) and Dungiven (Zone F) area.
Mainline drainage works substantially complete with outfall works to ponds ongoing at Burntollet (Zone B) and Dungiven. Side road drainage is ongoing at Dungiven and Drumahoe and further works to access tracks are continuing at Munreery (Zone E). Along with side road works ongoing at Tamnaherin, Drumahoe (Zone A) and Dungiven (Zone F).
Accommodation works are ongoing at Tamnaherin (Zone A) and Baranailt Rd (Zone D). Pavements works progressing from Tamnaherin to Claudy, with Claudy to Dungiven substantially complete with fencing operations ongoing around Tamnaherin.
NIW diversions and new installations are underway at Tamnaherin (Zone A) and landscaping activities ongoing throughout site. Line marking substantially complete from Claudy to Dungiven with works ongoing between Tamnaherin to Claudy. Signage and ITS to follow.
Structure 01
Substantially complete and being used by traffic
Structure 02
Substantially complete and being used by traffic
Structure 03
Paving and verge concrete to eastern verge to be completed mid-April 2022, being used by A6 traffic, side road works continue.
Structure 04
Substantially complete and being used by traffic
Structure 05A
Substantially complete and being used by traffic
Structure 05B
Verge infill, barrier installation and concrete to be completed mid-April 2022, surfacing ongoing.
Structure 07
Installation of kerbs, ducting and verge infill to be completed mid-April and ready for surfacing end-April 2022, side road works into June 2022.
Structure 08
Paving works ongoing planned to be available to traffic in June 2022.
Structure 09
Substantially complete being used by traffic
Structure 10
Kerbing, ducting and verge concrete to be completed early May 2022
Structure 11
Substantially complete, traffic flowing through side road
Structure 12
Substantially complete, traffic flowing through side road
Structure 13
Substantially complete, traffic flowing through access lane
Structure 14
Substantially Complete, traffic flowing through side road
Structure 15
Substantially complete traffic flowing through side road
Structure 16
Substantially Complete, traffic flowing through side road
Structure 17
Substantially complete
Structure 18
Substantially complete being used by traffic
Structure 19
Substantially complete being used by traffic
Structure 20
Substantially complete being used by traffic
Structure 21
Substantially complete being used by traffic
Structure 22
Substantially complete, traffic flowing through access lane