Progress Update January 2022

Jan 19, 2022 | News

 

 

 

Cut and fill operations are substantially complete with excavation works ongoing at Tamnaherin (Zone A) along with pond excavation works at Foreglen (Zone E). Mainline drainage outfall works at ponds is ongoing at Burntollet (Zone B) and Killunaght Rd (Zone E).

Further works to access tracks are continuing at Gortilea (Zone D) along with concreting of lanes and drainage works ongoing. Side roads are ongoing at various locations at Dungiven (Zone F) Tamnaherin junction, Ardmore and Fawney Rd (Zone A) Claudy junction (Zone D) and accommodation works are ongoing at Baranailt (Zone C) Dungiven (Zone F) and Tamnaherin Rd (Zone A).

Pavement operations are ongoing along with surfacing works between Claudy (Zone D) and Feeny Rd (Zone E). Fencing is ongoing between Gulf and Claudy (Zone C) west of Feeny Rd (Zone E) and Tamnaherin (Zone A) will follow in the coming weeks

NIW diversions and new installations are underway at Claudy Junction (Zone D) Ardmore Rd (Zone A) and Killunaght Rd (Zone E) along with BT ducting at Foreglen Rd (Zone E) and Claudy (Zone D). Landscaping is ongoing throughout the site, mostly tree and hedgerow planting and line markings to the new dual carriageway have started throughout the scheme.

Structure 01

Substantially complete and being used by traffic 

Structure 02

Waterproofing ongoing and preparing for verge infill and surfacing to start February 2022.

Structure 03

Northern wingwalls poured mid-January, parapet beams and parapet rails to be installed end of January 2022.

Structure 04

Substantially complete and being used by traffic

Structure 05A

Substantially complete and being used by traffic

Structure 05B

Pouring restraining slabs end of January 2022. Waterproofing, kerb and verge infill competition date approx. March and preparing for surfacing Mid-March 2022. 

Structure 07

Waterproofing to be completed mid- January and installation of kerbs, ducting and verge to be completed Mid-February.  Surfacing to commence March 2022.

Structure 08

Waterproofing completed mid- December, kerbs ducting and verge infill to be completed end of February and preparing for initial surfacing end of February 2022.

Structure 09

Substantially complete being used by traffic

Structure 10

Piling works to be completed end of January and retaining walls to be completed March 2022.

Structure 11

Substantially complete

Structure 12

Substantially complete

Structure 13

Substantially complete

Structure 14

Substantially Complete, traffic flowing through side road

Structure 15

Substantially complete

Structure 16

Substantially Complete, traffic flowing through side road

Structure 17

Substantially complete

Structure 18

Substantially complete being used by traffic

Structure 19

Substantially complete

Structure 20

Substantially complete being used by traffic

Structure 21

Waterproofing of deck to be completed end of January, kerbs, ducting and verge infill to be completed mid-February and ready for surfacing end of February 2022.

Structure 22

Substantially complete being used by traffic