Progress Update June 2020

Cut and fill operations are continuing at various locations across the scheme including Teeavan Road (Zone F) Ballyhaneden (Zone D) Gortilea, Brackfield and Burntollet (Zone B) Claudy Junction (Zone C) and last Drumahoe to Liberty Glen (Zone A).
Access tracks are continuing east of Burntollet (Zone B) Drumahoe (Zone A) Derrychrier (Zone E) along with the access track into The Oaks (Zone B).
The Teeavan side road is now open to traffic and side road drainage is continuing at Altagarron road (Zone E) and Tirbracken Road (Zone A).
At present, a new pathway is being constructed at Drumahoe Park and Ride and pavement works are ongoing in preparation for the opening of this section of the road.
Preparation for temporary diversion is currently underway to safely divert the main A6 traffic onto a new alignment from Ervey Road to Burntollet to facilitate the construction of Structure 04 approx. the end of June 2020.
Mainline drainage is ongoing at Feeny Road, Ovil Hill, (Zone E) CrocknaBrock (Zone E) Ervey Road and Burntollet (Zone B).
Grass seeding is ongoing throughout the scheme including hydro seeding adjacent to water courses and hedro maintenance. Batching plant has also started at Derrychrier (Zone E).
Structures
Structure 1 – Restraining slabs and waterproofing the deck
Structure 3 – Piling to commence
Structure 5 – Abutments on-going
Structure 7 – Abutments on-going
Structure 9 – East and West diaphragms to be poured
Structure 10 – Complete
Structure 11 – Backfilling/drainage and waterproofing of deck
Structure 13 – excavation for bases and upfill works
Structure 12- Preparation of North piling platform
Structure 14- Complete
Structure 16- Completion of wingwalls/ Commence structure backfill
Structure 17- Piling east/west abutments
Structure 18- Tying deck steel/ Pour north and south Diaphragm
Structure 19- Complete parapets, wingwalls and retaining slabs/ Commence structure backfill
Structure 20- Complete south abutment/ Placing of beams
Structure 21- Excavation of east central pier/ Tying steel on west abutment and pier
Structure 22- Pour north and south Diaphragm/ Pour deck