Structure 1 – Beam to be installed early March 2020

Structure 5- Piling installed and pouring concrete base early March 2020

Structure 8- Concrete base and abutment on the south side and excavation for centre pier

Structure 9- Commencing concrete base

Structure 11- Pour diaphragm to deck level

Please follow below link to timelapse video.

Gortilea Road Beam Installation Timelapse Video

Structure 16- Install pre-cast units and start wingwalls

Structure 18– Pour both abutments and centre pier

Structure 19- Pour diaphragm to deck level

Structure 21- Complete piles on east abutment

Structure 22- Install beams end of March 2020