Progress Update May 2020

May 7, 2020 | News

Structure 1 – Deck upstands and backfilling

Structure 5 – starting east and west abutment bases

Structure 8 – Pour south abutment

Structure 9 – Complete beam instalment and start wingwall construction and backfilling

Structure 10 – Construction works on going

Structure 11 – Complete wingwalls and backfilling

Structure 16– Construction of North and South wingwalls

Structure 18- Preparation for beam installation in the next month

Structure 19– Pour deck/parapets

Structure 20– Pour north and south abutment bases, intermediate base and columns

Structure 21– Installation of west abutment piles

Structure 22– Tying diaphragm and deck steel