Progress Update May 2020

Structure 1 – Deck upstands and backfilling
Structure 5 – starting east and west abutment bases
Structure 8 – Pour south abutment
Structure 9 – Complete beam instalment and start wingwall construction and backfilling
Structure 10 – Construction works on going
Structure 11 – Complete wingwalls and backfilling
Structure 16– Construction of North and South wingwalls
Structure 18- Preparation for beam installation in the next month
Structure 19– Pour deck/parapets
Structure 20– Pour north and south abutment bases, intermediate base and columns
Structure 21– Installation of west abutment piles
Structure 22– Tying diaphragm and deck steel