Progress Update May 2021

Cut and fill operations are ongoing at Tamnaherin (Zone A), The Oaks, Brackfield (Zone B) Ovil Hill, Killunaght, Feeny Road (Zone E) and Ballyhanedin to Claudy (Zone D).
Mainline drainage is ongoing between Gorilea and Claudy (Zone D) Ballyhanedin (Zone D) and Feeny Road (Zone E). Culvert works are continuing at Baranailt Road North (Zone C) and fencing is ongoing at Crock Na Brock, Munreery (Zone D) and Brackfield (Zone B).
Further side roads have commenced at Baranailt Road South (Zone D). Feeny side road (Zone E) tie-in works are now complete and the Magheramore side road (Zone F) tie in works are progressing. Ballyhanedin side road (Zone D) embankment is now complete, and drainage and pavement works will continue the next few weeks.
Gortilea (Zone D) drainage complete and pavement works are ongoing in the next few weeks.
Construction work at Dungiven roundabout is ongoing, including utilities and drainage works, particularly around Tracy’s way.
Access tracks complete West of Derrychrier (Zone E) and East of Feeny road (Zone F) with access track works ongoing at Munreery, Gortilea (Zone D) and Brackfield (Zone B). Accommodation works are ongoing around Feeny Road (Zone E).
NIW services are working at Baranailt Road (Zone D) Gulf Road, (Zone B) Fawney Road (Zone A) and Ballyhanedin Road (Zone D), along with a variety of utility diversions to facilitate the construction of the new roundabout in Dungiven.
Landscape planting is now complete for the season and grass seeding and maintenance has been ongoing since May 2021.
Structures Update
Structure 1: Complete
Structure 2: Structure 2 – Placing Beams May 2021
Structure 3: Pouring diaphragms end of May 2021
Structure 4: Preparing to pour North & South restraining slabs
Structure 5A: Complete
Structure 5B: West and East Abutment concrete pour end of May 2021
Structure 7: Beams installed and preparing deck for concrete pour end of May 2021
Structure 8: Pouring concrete base end of May 2021.
Structure 9: Complete
Structure 10: Complete
Structure 11: Preparing for waterproofing and pouring concrete
Structure 12: Pouring restraining slabs
Structure 13: Restraining slabs to be poured Mid May 2021
Structure 14: Complete
Structure 15: Wingwalls to be poured end of May 2021
Structure 16: Complete
Structure 17: Deck Pours complete, Wingwalls to be completed the beginning of June 2021
Structure 18: Complete
Structure 19: Complete
Structure 20: Complete
Structure 21: Preparing beam installation end of May 2021
Structure 22: Complete