Altagarron and Crock Na Brock Road Closure 

The Altagarron and Crock Na Brock Road will close to all road users from the 12th November for approximately 6 months.

This traffic management is required to facilitate the excavation and replacement of material under the footprint of the existing road.  This will provide a suitable foundation to construct the side road structure S14 Altagarron Road Underbridge.

The closure will also facilitate the movement of unsuitable material including peat to allocated tip areas.

A signed diversion will be in place via the Ballyhenedin Road.  The Diversion will operate in both directions.

Temporary Traffic Management to take place across the A6 mainline

There will be temporary traffic management in the following locations from 12th November 2018 for approximately 2 weeks to facilitate Geotechnical Investigations.

  • Wide grass verge adjacent to Tirbracken junction with A6
  • A6 west bound between Burntoliet and Tamnaherin Road
  • A6 east bound 400m west of Claudy junction
  • West bound lane and verge closure for approximately 2 days between the hours of 9-30-16.00 for safety zone.